CLAT 2020 | Legal Reasoning

Legal Reasoning | Previous Year Questions

CLAT Legal Reasoning

As the name indicates, CLAT Legal Reasoning section has a distinct element of law. To crack these questions, ideally, a candidate has to keep reading any news and opinion articles from at least one newspaper. A basic idea regarding the Current Affairs of legal issues will drastically improve the reading speed and comprehension. Though deeper understanding of law is not mandatory, keeping oneself abreast of the current happenings will prove to a competitive edge. The passages have been selected carefully to encompass a legal context in them.

As with the CLAT Logical Reasoning section and the CLAT English Language section, adequate attention has been given to ensure the passages are from a range of topics. Needless to say, the questions are pegged exactly at the level of difficulty of CLAT, with an eye on the samples published by the Consortium of NLUs.

Enough said. In for some serious Legal Reasoning? Let’s get cracking!

CLAT 2020 Legal Reasoning: COVID-19 induced 'Force Majeure' in Contracts

The COVID-19 pandemic has taken the entire world hostage in less than four months, and the global economy has been hit the hardest with governments across the globe implementing stringent policies including lockdown to control the coronavirus outbreak. The pandemic today presents unprecedented challenges and impediments to businesses in conducting their normal operations. The lockdown across the world has caused delays in the performance of contracts and transactions. Now, the question that arises is whether the current situation can enable parties to a contract to alter their obligations with non-compliance of terms neither being regarded as a "default committed by any party" nor a "breach of contract"? There are certain well-accepted practices for dealing with such extraordinary situations in commercial transactions by the inclusion of force majeure & material adverse effect (MAE) clauses. Determination of the types of circumstances so covered by the force majeure clause contained in a contract is essential. Provisions of force majeure often cover natural disasters like hurricanes, floods, and earthquakes as "acts of God." Other covered events may include war, terrorism, civil disorder, fire, disease medical epidemics or by reasons of applicable laws or regulations. Broadly, the Courts have interpreted the term "Force Majeure" as an event that can neither be anticipated nor controlled by either of the contracting parties. A force majeure clause applies in the context of ongoing contractual arrangements, whereas, an MAE or material adverse change (MAC) clause applies to the allocation of risk in transactions before their closure or completion. Pandemic and related consequences such as government action is a type of event covered by a force majeure clause, however, its impact on the affected party's ability to perform its contractual obligations may vary depending upon contractual terms. It is common for force majeure clauses to specify the impact that the event or circumstances in question must have, in order for the clause to be triggered. References may be made, for example, to the event or circumstances having "prevented", "hindered" or "delayed" performance. These terms require different levels of impact on performance before a party can claim recourse to these clauses. In other words, the force majeure and MAC clauses act as an exception to what would otherwise be treated as a breach of contract. Certain contracts may state that, if a force majeure clause is applied, the contract may automatically be terminated. On the other hand, some contracts may even state that the duty to fulfil the contractual obligation may be suspended for a certain period of time and if the force majeure event is not curbed or treated even after such time, then eventually the contract may be terminated. Though there cannot be a one-size-fits-all solution to this question, and it depends upon how the force majeure clause is worded in a specific contract; and in the absence of the same, applicable laws related to the same will be required to be taken into consideration.
[Excerpt from Business Today, by Ranjana Roy Gawai, April 17, 2020]

In the same fact situation as mentioned above with a modification that there is a Force Majeure Clause in the Contract between A and B, let us suppose, that B, who was to supply goods to A on certain date and time, faced issues in relation to procurement of goods due to mill strike and also because of rise in prices of goods. In this case, can B claim the suspension of performance of Contract on the basis of the Force Majeure Clause?

  1. Yes, B can, depending upon the way, the Force Majeure Clause is worded.
  2. Such situation cannot be covered under Force Majeure as it is just a case of disappointed expectations and hence B cannot invoke the clause. It is merely a case of commercial hardship.
  3. B can invoke the Force Majeure clause as the clause is too broad to cover such situations.
  4. None of the above.

Explanatory Answer

“Provisions of force majeure often cover natural disasters like hurricanes, floods, and earthquakes as "acts of God." Other covered events may include war, terrorism, civil disorder, fire, disease medical epidemics or by reasons of applicable laws or regulations.” Clearly, mill-strike and price-rise are only commercial hardships that have an effect on the performance of the contract. They arise out of the design and flexibility of the supply chain of the contracting parties. Hence, Force Majeure cannot be invoked.

ICFAI Business School 2IIM CAT Online Coaching Classes 2IIM CAT Online Coaching Classes