CAT 2022 Quant was dominated by Arithmetic followed by Algebra. In Arithmetic, the questions were dominated by topics like Speed-time-distance, Mixture and Alligations. This year, there was a surprise. The questions from Geometry were relatively on the lower side as compared to the previous years. There were 8 TITA Qs this year. Overall this section was at a medium level of difficulty.

Question 3 : Bob can finish a job in 40 days, if he works alone. Alex is twice as fast as Bob and thrice as fast as Cole in the same job. Suppose Alex and Bob work together on the first day, Bob and Cole work together on the second day, Cole and Alex work together on the third day, and then, they continue the work by repeating this three-day roster, with Alex and Bob working together on the fourth day, and so on. Then, the total number of days Alex would have worked when the job gets finished, is


🎉🎉Grab a Diwali Discount of up to ₹ 12,000 on 2025 CAT courses! Offer valid until 31st October.


Register Now

🎉 Supercharge the final leg of your CAT journey with our Percentile Booster – the push you need for top scores! 🎉


Register Now


Video Explanation


Best CAT Coaching in Chennai


CAT Coaching in Chennai - CAT 2022
Limited Seats Available - Register Now!


Explanatory Answer

Since Alex is twice as fast as Bob and thrice as fast as Cole, let us assume that the work done by Alex in a day as 6x.
This means that the work done by Bob and Cole in a day is 3x and 2x respectively.

Alex
Bob
Cole
6x
3x
2x
Since Bob can finish the job in 40 days working alone, the quantum of work to finish the job = 40 \( \times \) 3x = 120x
The work done on the first day, the second day, and the third day is as follows.
Day 1
(Alex & Bob)
Day 2
(Bob & Cole)
Day 3
(Cole & Alex)
9x
5x
8x
The total work done in one cycle of 3 days = 9x + 5x + 8x = 22x
120x = 22x(5) + 9x + 1x
This means, it takes 5 complete cycles of 3 days, a full Day 1 and Day 2 to finish the job.
In one cycle Alex works twice, on Day 1 and Day 3.
So the total number of days that Alex works = 2(5) = 1 = 11 days


The answer is '11'

CAT Questions | CAT Quantitative Aptitude

CAT Questions | Verbal Ability for CAT


Where is 2IIM located?

2IIM Online CAT Coaching
A Fermat Education Initiative,
58/16, Indira Gandhi Street,
Kaveri Rangan Nagar, Saligramam, Chennai 600 093

How to reach 2IIM?

Mobile: (91) 99626 48484 / 94459 38484
WhatsApp: WhatsApp Now
Email: info@2iim.com