CAT 2023 Question Paper | Quant Slot 3

CAT Previous Year Paper | CAT Quant Questions | Question 8

CAT 2023 Quant was dominated by Arithmetic followed by Algebra. In Arithmetic, the questions were dominated by topics like Speed-time-distance, Mixture and Alligations. This year, there was a surprise. The questions from Geometry were relatively on the lower side as compared to the previous years. There were 8 TITA Qs this year. Overall this section was at a medium level of difficulty.

Question 8 : Rahul, Rakshita and Gurmeet, working together, would have taken more than 7 days to finish a job. On the other hand, Rahul and Gurmeet, working together would have taken less than 15 days to finish the job. However, they all worked together for 6 days, followed by Rakshita, who worked alone for 3 more days to finish the job. If Rakshita had worked alone on the job then the number of days she would have taken to finish the job, cannot be

  1. 17
  2. 21
  3. 16
  4. 20

🎉 Flat ₹ 8,000 off on our CAT '24 & '25 Courses!
Valid till 30th April


Register Now

Best CAT Online Coaching
Try upto 40 hours for free
Learn from the best!


2IIM : Best Online CAT Coaching.


Video Explanation


Best CAT Coaching in Chennai


CAT Coaching in Chennai - CAT 2022
Limited Seats Available - Register Now!


Explanatory Answer

Let Rahul, Rakshita and Gurmeet take A, B and C days respectively to finish the job on their own, this means, in one day, the fraction of work done by Rahul, Rakshita and Gurmeet is \( \frac { 1 } { A } , \frac { 1 } { B } , \frac { 1 } { C } \).
Rahul, Rakshita and Gurmeet, working together, would have taken more than 7 days to finish a job.
This means, the fraction of work done by all three of them, together, in one day, is less than \( \frac { 1 } { 7 } \).
\( \frac { 1 } { A } + \frac { 1 } { B } + \frac { 1 } { C } < \frac { 1 } { 7 } \)
However, they all worked together for 6 days, followed by Rakshita, who worked alone for 3 more days to finish the job.
6 × (the fraction of work done by them together in one day) + 3 × (the fraction of work done by Rakshita in one day) = (one full job)
\( 6 \left( \frac { 1 } { A } + \frac { 1 } { B } + \frac { 1 } { C } \right) + \frac { 3 } { B } = 1 \)
\( \frac { 3 } { B } = 1 - 6 \left( \frac { 1 } { A } + \frac { 1 } { B } + \frac { 1 } { C } \right) \)
But, we know that, \( \frac { 1 } { A } + \frac { 1 } { B } + \frac { 1 } { C } < \frac { 1 } { 7 } \)
\( \frac { 3 } { B } > 1 - \frac { 6 } { 7 } \)
\( \frac { 1 } { B } > \frac { 1 } { 21 } \)
\( B < 21 \)
So, Rakshita should take less than 21 days to finish the job.
The extra information can be used to find the lower bound of B.
On the other hand, Rahul and Gurmeet, working together would have taken less than 15 days to finish the job.
\( \frac { 1 } { A } + \frac { 1 } { c } > \frac { 1 } { 15 } \)
But, we know that, \( \frac { 1 } { A } + \frac { 1 } { B } + \frac { 1 } { C } < \frac { 1 } { 7 } \)
So, the maximum value of \( \frac { 1 } { B } = \frac { 1 } { 7 } - \frac { 1 } { 15 } = \frac { 8 } { 7 ( 15 ) } \).
The minimum value of B = 13.125


The question is " Rahul, Rakshita and Gurmeet, working together, would have taken more than 7 days to finish a job. On the other hand, Rahul and Gurmeet, working together would have taken less than 15 days to finish the job. However, they all worked together for 6 days, followed by Rakshita, who worked alone for 3 more days to finish the job. If Rakshita had worked alone on the job then the number of days she would have taken to finish the job, cannot be "

The answer is '21'

Choice B is the correct answer.

CAT Questions | CAT Quantitative Aptitude

CAT Questions | CAT DILR

CAT Questions | Verbal Ability for CAT


Where is 2IIM located?

2IIM Online CAT Coaching
A Fermat Education Initiative,
58/16, Indira Gandhi Street,
Kaveri Rangan Nagar, Saligramam, Chennai 600 093

How to reach 2IIM?

Mobile: (91) 99626 48484 / 94459 38484
WhatsApp: WhatsApp Now
Email: info@2iim.com