🎉 Ace XAT 2025 with 2IIM's Crash Course - Enrol now


CAT 2017 Question Paper | Quants Slot 1

CAT Previous Year Paper | CAT Pipes and Cisterns Questions | Question 2

This is a question from Time and Work. One can usually expect 2 to 3 questions from this idea in the CAT Question Paper. A person starts doing a job. From the following day a new person starts joining him everyday. Would they be able to finish the work on time? To check out about 1000+ fabulous CAT Level questions with detailed video solutions for free, go here: CAT Question Bank

Question 2 : A person can complete a job in 120 days. He works alone on Day 1. On Day 2, he is joined by another person who also can complete the job in exactly 120 days. On Day 3, they are joined by another person of equal efficiency. Like this, everyday a new person with the same efficiency joins the work. How many days are required to complete the job? [TITA]


🎉 Ace XAT 2025 with 2IIM's Crash Course - Enrol now


Best CAT Online Coaching
Try upto 40 hours for free
Learn from the best!


2IIM : Best Online CAT Coaching.


Video Explanation


Best CAT Coaching in Chennai


CAT Coaching in Chennai - CAT 2022
Limited Seats Available - Register Now!


Explanatory Answer

Method of solving this CAT Question from Pipes and Cisterns

Given that a person can complete a job in 120 days.
He works alone on Day 1.
On Day 2, he is joined by another person who also can complete the job in exactly 120 days.
On Day 3, they are joined by another person of equal efficiency.
Everyday a new person with the same efficiency joins the work
So by first day 1 person
Similarly by second day 2
Third day 3 and it goes on.......until it makes a total of 120
We have to find how many days are required to complete the job
So \\frac{15 × 16}{2}) = 120 [by \\frac{n(n+1)}{2})]
So 1 + 2 + 3 + 4 ...... till 15 days are required to complete this Job.
This will get completed in 15 days.
Hence 15 days are required to complete the job

The question is "A person can complete a job in 120 days. He works alone on Day 1. On Day 2, he is joined by another person who also can complete the job in exactly 120 days. On Day 3, they are joined by another person of equal efficiency. Like this, everyday a new person with the same efficiency joins the work. How many days are required to complete the job? [TITA]"

Hence, the answer is 15

 

CAT Questions | CAT Quantitative Aptitude

CAT Questions | Verbal Ability for CAT


Where is 2IIM located?

2IIM Online CAT Coaching
A Fermat Education Initiative,
58/16, Indira Gandhi Street,
Kaveri Rangan Nagar, Saligramam, Chennai 600 093

How to reach 2IIM?

Mobile: (91) 99626 48484 / 94459 38484
WhatsApp: WhatsApp Now
Email: info@2iim.com