Questions from Work and Time have a lot of variety, making it slightly difficult with regards to Arithmetic. However, many such questions from CAT Previous Year Paper
might not be as frightening as they seems to be. Here's such a question which might seem a bit tricky, but if you get the concept right, you are through! Solve more such interesting questions by visiting 2IIM's CAT Question Bank.Question 22 : Ramesh and Ganesh can together complete a work in 16 days. After seven days of working together, Ramesh got sick and his efficiency fell by 30%. As a result, they completed the work in 17 days instead of 16 days. If Ganesh had worked alone after Ramesh got sick, in how many days would he have completed the remaining work?
Given that Ramesh and Ganesh can together complete a work in 16 days
After seven days of working together, Ramesh got sick and his efficiency fell by 30%.
To the original schedule of 16 days there are 9 more days and in this 9 days Ramesh fall short by 9 × 0.3x = 2.7x where x is the work done by Ramesh in a day
So the change = 2.7x (i.e. the gap because of drop in efficiency)
This 2.7x is compensated by one day of Ganesh + another 0.7 of Ramesh
2.7x = G + 0.7 x (Because the last day also he works with reduced efficiency)
2x = G
Hence Ganesh works twice as that of Ramesh.
If Ganesh had worked alone after Ramesh got sick means in the 7 days Ramesh would have completed \\frac{7}{48}) of the task
Ganesh on each day can do \\frac{1}{24}) of the task
Task to be completed by Ganesh is \\frac{41}{48}) completely
One day he can complete \\frac{1}{24}) so \\frac{41}{48}) × \\frac{24}{1}) = 20.5 days
If Ganesh had worked alone after Ramesh got sick, the no.of days needed for completing the remaining work is 20.5 – 7 = 13.5 days
The question is "Ramesh and Ganesh can together complete a work in 16 days. After seven days of working together, Ramesh got sick and his efficiency fell by 30%. As a result, they completed the work in 17 days instead of 16 days. If Ganesh had worked alone after Ramesh got sick, in how many days would he have completed the remaining work?"
Choice C is the correct answer.
Copyrights © All Rights Reserved by 2IIM.com - A Fermat Education Initiative.
Privacy Policy | Terms & Conditions
CAT® (Common Admission Test) is a registered trademark of the Indian Institutes of Management. This website is not endorsed or approved by IIMs.
2IIM Online CAT Coaching
A Fermat Education Initiative,
58/16, Indira Gandhi Street,
Kaveri Rangan Nagar, Saligramam, Chennai 600 093
Mobile: (91) 99626 48484 / 94459 38484
WhatsApp: WhatsApp Now
Email: info@2iim.com